[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139939":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139939,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500—2013），施工企业综合单价的计算有以下工作，①测算人、料、机的数量；②确定组合定额子目；③计算各子目工程量；④计算清单项目的管理费和利润；⑤确定人、料、机单价；⑥计算清单项目的人、料、机总费用，正确的步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-③-②-⑥-⑤-④",false,{"key":16,"text":17,"correct":18},"B","②-③-①-⑤-⑥-④",true,{"key":20,"text":21,"correct":14},"C","③-①-②-⑥-⑤-④",{"key":23,"text":24,"correct":14},"D","①-③-②-④-⑥-⑤","本题考查的是清单综合单价编制的顺序。确定组合定额子目；计算定额子目工程量；测算人、料、机消耗量；确定人、料、机单价；计算清单项目的人、料、机总费用；计算清单项目的管理费和利润；计算清单项目的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]