[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139936,798,1,"单选题","下列选项中，关于风险率的说法不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标文件中要求投标人承担的风险费用，投标人应在综合单价中予以考虑",false,{"key":16,"text":17,"correct":18},"B","招标文件中未明确投标人要承担风险，投标人可完全不考虑风险费",true,{"key":20,"text":21,"correct":14},"C","风险费通常以风险费率的形式进行计算",{"key":23,"text":24,"correct":14},"D","当出现的风险内容在招标文件规定的风险范围内时，合同价款不做调整","招标文件中要求投标人承担的风险费用，投标人应在综合单价中予以考虑，通常以风险费率的形式进行计算。在施工过程中，当出现的风险内容及其范围（幅度）在招标文件规定的范围（幅度）内时，综合单价不得变动，合同价款不做调整。招标文件中未明确投标人要承担风险，投标人也应适当考虑风险费。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]