[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139933":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139933,798,1,"单选题","下列选项中，应采用分包法计价的措施项目费是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","室内空气污染测试",true,{"key":16,"text":17,"correct":18},"B","二次搬运费",false,{"key":20,"text":21,"correct":18},"C","混凝土模板工程",{"key":23,"text":24,"correct":18},"D","安全文明施工费","措施项目费的计算方法： （1）综合单价法：混凝土模板、脚手架、垂直运输 （2）参数法计价：安全文明施工费、夜间施工增加费、二次搬运费、冬雨季施工增加费、已完工程及设备保护费。 （3）分包法计价： 能独立分包的项目，如室内空气污染测试。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]