[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139932":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139932,798,1,"单选题","综合单价的计算步骤包括：①计算清单项目的管理费和利润；②计算定额子目工程量③确定组合定额子目；④计算清单项目的综合单价；⑤测算人料机消耗量；⑥确定人、料、机单价；⑦计算人料机总费用。则排列正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","③②⑤⑥⑦①④",true,{"key":16,"text":17,"correct":18},"B","③⑤⑥②①⑦④",false,{"key":20,"text":21,"correct":18},"C","⑤⑥②①⑦④③",{"key":23,"text":24,"correct":18},"D","⑤①⑦④⑤⑥②","综合单价的计算步骤：①确定组合定额子目；②计算定额子目工程量； ③测算人料机消耗量；④确定人、料、机单价；⑤计算人料机总费用；⑥计算清单项目费管理费和利润；⑦计算清单项目的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]