[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139930":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139930,798,2,"多选题","根据《建设工程工程量清单计价规范》（GB50500-2013），关于工程量清单编制的说法，正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","使用国有资金投资的建设工程发承包，宜采用工程量清单计价",false,{"key":16,"text":17,"correct":14},"B","投标人按照工程量清单所表述的内容,依据企业定额计算投标价格,自主填报工程量清单所列项目的工程量、单价与合价",{"key":19,"text":20,"correct":21},"C","工程量清单是工程付款和结算的依据",true,{"key":23,"text":24,"correct":21},"D","工程量清单是调整工程价款、处理工程索赔的依据",{"key":26,"text":27,"correct":21},"E","招标工程量清单必须作为招标文件的组成部分，由招标人提供，并对其准确性和完整性负责","CDE","本题考查工程量清单编制的相关规定。A选项，使用国有资金投资的建设工程发承包，必须采用工程量清单计价；非国有资金投资的建设工程，宜采用工程量清单计价。B选项，投标人按照工程量清单所表述的内容，依据企业定额计算投标价格，自主填报工程量清单所列项目的单价与合价。工程量是由招标人填写的。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]