[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139929":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139929,798,2,"多选题","根据《建设工程工程量清单计价规范》（GB50500-2013），下列属于工程量清单编制的依据的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","拟定的招标文件",true,{"key":16,"text":17,"correct":18},"B","类似项目的投标文件",false,{"key":20,"text":21,"correct":14},"C","行业主管部门颁发的计价定额和方法",{"key":23,"text":24,"correct":14},"D","工程特点及常规的施工方案",{"key":26,"text":27,"correct":18},"E","工程造价管理机构发布的工程造价信息及相关市场价格","ACD","本题考查招标工程量清单的编制依据。招标工程量清单编制的依据有:(1)《建设工程工程量清单计价规范》和相关工程的国家计量规范；(2)国家或省级、行业建设主管部门颁发的计价定额和办法；(3)建设工程设计文件及相关材料；(4)与建设工程有关的标准、规范、技术资料；(5)拟定的招标文件；(6)施工现场情况、地勘水文资料、工程特点及常规施工方案；(7)其他相关资料。E选项，是编制招标控制价的依据。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]