[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139928,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），编制投标文件时，招标文件中已提供暂估价的材料价格应根据（ ）计入综合单价。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投标人自主确定价格",false,{"key":16,"text":17,"correct":14},"B","投标时当地的市场价格",{"key":19,"text":20,"correct":21},"C","招标文件列出的单价",true,{"key":23,"text":24,"correct":14},"D","政府主管部门公布的价格","暂列金额和暂估价由招标人按估算金额确定。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]