[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139927":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139927,798,1,"单选题","根据《建筑工程工程量清单计价规范》（GB50500-2013），分部分项工程量清单中项目名称确定方法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以工程实体命名",false,{"key":16,"text":17,"correct":14},"B","按照《计量规范》中规定的项目名称确定",{"key":19,"text":20,"correct":21},"C","根据《计量规范》的项目名称结合拟建工程的实际确定",true,{"key":23,"text":24,"correct":14},"D","根据工程经验确定","本题考查的是分部分项工程项目名称的确定。分部分项工程量清单的项目名称应根据《计量规范》的项目名称结合拟建工程的实际确定。《计量规范》中规定的“项目名称”为分项工程项目名称，一般以工程实体命名。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]