[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139924":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139924,798,1,"单选题","根据《建设工程量清单计价规范》(GB50500-2013)编制的工程量清单中，某分部分项工程的项目编码010302004005，则“01”的含义是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程顺序码",false,{"key":16,"text":17,"correct":14},"B","分部工程顺序码",{"key":19,"text":20,"correct":14},"C","专业工程顺序码",{"key":22,"text":23,"correct":24},"D","国家计量规范代码",true,"1、2 位为相关工程国家计量规范代码；3、4 位为专业工程顺序码；5、6位为分部工程顺序码；7、8、9 位为分项工程顺序码；10、11、12 位为清单项目名称顺序码。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]