[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139913":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139913,798,1,"单选题","设计概算是设计单位编制和确定的建设工程项目从（ ）至（ ）所需全部费用的文件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","筹建，办理完竣工决算",false,{"key":16,"text":17,"correct":18},"B","筹建，竣工交付使用",true,{"key":20,"text":21,"correct":14},"C","设计，项目报废",{"key":23,"text":24,"correct":14},"D","设计，施工保修期满","设计概算是在投资估算的控制下由设计单位根据初步设计或扩大初步设计的图纸及说明，利用国家或地区颁发的概算指标、概算定额、综合指标预算定额、各项费用定额或取费标准（指标）、建设地区自然、技术经济条件和设备材料预算价格等资料，按照设计要求，对建设项目从筹建至竣工交付使用所需全部费用进行的概略计算。设计概算的成果文件称作设计概算书，也简称设计概算。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]