[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139906":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139906,798,1,"单选题","完成某预算定额项目单位工程量的基本用工为5.6 工日，辅助用工为1.4 工日，超运距用工为1.8 工日，人工幅度差系数为10%，该定额的人工工日消耗量为（ ）工日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","9.68",true,{"key":16,"text":17,"correct":18},"B","9.50",false,{"key":20,"text":21,"correct":18},"C","9.12",{"key":23,"text":24,"correct":18},"D","9.36","人工工日消耗量=（基本用工+辅助用工+超运距用工）×（1+人工幅度差系数）=（5.6+1.4+1.8）×（1+10%）=9.68 工日。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]