[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139905":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139905,798,1,"单选题","下列不属于编制人工定额时需要拟定正常的施工作业条件的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟定施工作业的时间",true,{"key":16,"text":17,"correct":18},"B","拟定施工作业的内容",false,{"key":20,"text":21,"correct":18},"C","拟定施工作业地点的组织",{"key":23,"text":24,"correct":18},"D","拟定施工作业人员的组织","本题考查的是人工定额的编制——拟定正常的施工作业条件。拟定施工的正常条件包括:拟定施工作业的内容；拟定施工作业的方法；拟定施工作业地点的组织；拟定施工作业人员的组织等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]