[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139901,798,1,"单选题","编制机械台班使用定额时，属于非施工本身造成的停工时间的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","筑路机在工作区末端调头的无负荷工作时间",false,{"key":16,"text":17,"correct":14},"B","把灰浆泵从一个工作地点转移到另一工作地点的工作中断时间",{"key":19,"text":20,"correct":14},"C","由于未及时供给机械燃料而引起的停工时间",{"key":22,"text":23,"correct":24},"D","暴雨引起的压路机的停工时间",true,"本题考查机械台班使用定额机械工作时间消耗的分类。筑路机在工作区末端调头无负荷工作时间属于不可避免的无负荷工作时间；把灰浆泵从一个工作地点转移到另一工作地点的工作中断时间属于与工艺过程有关的不可避免中断工作的时间；由于未及时供给机械燃料而引起的停工，属于施工本身造成的停工时间；暴雨引起的压路机的停工属于非施工本身造成的停工时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]