[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139891":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139891,798,2,"多选题","估算建设项目设备购置费时，可以作为设备原价的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","国产标准设备成本价",false,{"key":16,"text":17,"correct":18},"B","国产标准设备出厂价",true,{"key":20,"text":21,"correct":18},"C","国产标准设备订货合同价",{"key":23,"text":24,"correct":18},"D","进口设备抵岸价",{"key":26,"text":27,"correct":14},"E","进口设备出厂价","BCD","国产标准设备原价一般指的是设备制造厂的交货价，即出厂价。如设备由设备成套公司供应，则以订货合同价为设备原价。有的设备有两种出厂价，即带有备件的出厂价和不带有备件的出厂价。在计算设备原价时，一般按带有备件的出厂价计算。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]