[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139882,798,1,"单选题","某建设工程项目购置的进口设备采用装运港船上交货价，属于卖方责任的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","办理出口手续",true,{"key":16,"text":17,"correct":18},"B","租赁船只",false,{"key":20,"text":21,"correct":18},"C","办理运输保险",{"key":23,"text":24,"correct":18},"D","承担货物装船后的一切风险","本题考查的是装运港船上交货卖方需承担的责任。采用装运港船上交货价(FOB)时卖方的责任是：负责在合同规定的装运港口和规定的期限内，将货物装上买方指定的船只并及时通知买方；负责货物装船前的一切费用和风险；负责办理出口手续；提供出口国政府或有关方面签发的证件；负责提供有关装运单据。买方的责任是，负责租船或订舱，支付运费，并将船期、船名通知卖方；承担货物装船后的一切费用和风险；负责办理保险及支付保险费，办理在目的港的进和收货手续；接受卖方提供的有关装运单据，并按合同规定支付货款。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]