[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139881":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139881,798,1,"单选题","国家计量规范规定不宜计量的措施项目费不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","已完工程及设备保护费",false,{"key":16,"text":17,"correct":14},"B","安全文明施工费",{"key":19,"text":20,"correct":21},"C","脚手架工程费",true,{"key":23,"text":24,"correct":14},"D","冬雨季施工增加费","本题考查的是不宜计量的措施项目费。不宜计量的措施项目费包括：安全文明施工费、夜间施工增加费、二次搬运费、冬雨季施工增加费、已完工程及设备保护费。C选项属于可以计量的措施项目费。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]