[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139879":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139879,798,1,"单选题","下列工程项目投资中，属于静态投资的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","铺底流动资金",false,{"key":16,"text":17,"correct":14},"B","价差预备费",{"key":19,"text":20,"correct":14},"C","建设期利息",{"key":22,"text":23,"correct":24},"D","设备购置费",true,"本题考查的是建设投资中的静态投资部分。建设投资可以分为静态投资部分和动态投资部分。静态投资部分由建筑安装工程费、设备及工器具购置费、工程建设其他费构成。动态投资部分，是指在建设期内，因建设期利息和国家新批准的税费、汇率、利率变动以及建设期价格变动引起的建设投资增加额，包括价差预备费、建设期利息等。而设备购置费属于工程费用，因此是静态的费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]