[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139877":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139877,798,1,"单选题","关于建设单位的场地准备和临时设施费的说法，不正确的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应尽量与永久性工程统一考虑",false,{"key":16,"text":17,"correct":14},"B","改扩建项目一般只计拆除清理费",{"key":19,"text":20,"correct":14},"C","新建项目的场地准备及临时设施费可以按工程费用的比例计算",{"key":22,"text":23,"correct":24},"D","建设场地的大型土石方应计入场地准备费用",true,"场地准备及临时设施应尽量与永久性工程统一考虑。建设场地的大型土石方工程应进入工程费用中的总图运输费用中。新建项目的场地准备及临时设施费应根据实际工程量估算，或按工程费用的比例计算。改扩建项目一般只计拆除清理费。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]