[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139814":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139814,798,1,"单选题","某工程需要材料，这批材料的加工方式有两种，方案一需要固定成本10 万元，每吨加工费用为100 元；方案二需要固定成本8 万元，每吨加工费用为150 元，则从经济上考虑，优先考虑方案一的情况是材料加工量为（ ）吨。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","420",true,{"key":16,"text":17,"correct":18},"B","380",false,{"key":20,"text":21,"correct":18},"C","340",{"key":23,"text":24,"correct":18},"D","300","方案一：成本=10 万+100Q； 方案二：成本=8 万+150Q； 优先考虑方案一，则方案一成本比方案二小。即: 10 万+100Q 2 万； Q>400 吨。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]