[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139809":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139809,798,2,"多选题","价值工程在分析阶段的主要工作内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","功能定义",true,{"key":16,"text":17,"correct":14},"B","功能整理",{"key":19,"text":20,"correct":21},"C","方案创造",false,{"key":23,"text":24,"correct":21},"D","方案审批",{"key":26,"text":27,"correct":14},"E","功能评价","ABE","分析阶段的主要工作内容包括：功能定义、功能整理、功能评价。方案创造是创新阶段的工作内容；方案审批是实施阶段的工作内容。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]