[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139788":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139788,798,2,"多选题","若选定静态评价指标进行技术方案敏感性分析，可以选择（ ）作为不确定性因素。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投资额",true,{"key":16,"text":17,"correct":18},"B","折现率",false,{"key":20,"text":21,"correct":14},"C","生产期",{"key":23,"text":24,"correct":14},"D","产品单价",{"key":26,"text":27,"correct":14},"E","建设期限","ACDE","本题考查敏感性分析的不确定性因素的选择。选择的因素要与选定的分析指标相联系。否则，当不确定性因素变化一定幅度时，并不能反映评价指标的相应变化，达不到敏感性分析的目的。比如折现率因素对静态评价指标不起作用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]