[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139758,798,1,"单选题","关于工程量清单招标中计日工报价技巧的说法，正确的是（）。 (2013)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单纯对计日工程报价应报低价",false,{"key":16,"text":17,"correct":14},"B","招标文件中有名义工程量的计日工程报高价",{"key":19,"text":20,"correct":21},"C","单纯对计日工程报价应报高价",true,{"key":23,"text":24,"correct":14},"D","招标文件中有名义工程量的计日工应报低价","如果单纯对计日工报价，可以报高一些，以便日后业主用工或使用机械时可以多盈利。但如果招标文件有一个假定的“名义工程量”时，则需要具体分析是否报高价，以免提高总报价。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]