[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139755,798,1,"单选题","关于国际工程投标报价中暂定金额的说法，错误的是( )。 (2014)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂定金额是业主在招标文件中明确规定了数额的一笔资金",false,{"key":16,"text":17,"correct":14},"B","承包商在投标报价时应将暂定金额计入工程总报价",{"key":19,"text":20,"correct":21},"C","暂定金额等同于暂估价",true,{"key":23,"text":24,"correct":14},"D","承包商无权做主使用暂定金额","暂定金额是业主在招标文件中明确规定了数额的一笔资金，标明用于工程施工，或供应货物与材料，或提供服务，或以应付意外情况，亦称待定金额或备用金。每个承包商在投标报价时均应将此暂定金额数计入工程总报价，但承包商无权做主使用此金额，这些项目的费用将按照业主工程师的指示与决定，全部或部分使用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]