[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139753":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139753,798,2,"多选题","关于国际工程招标中暂定金额的说法，正确的有（）（2016）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包商在投标报价时应将暂定金额在总报价之外单列",false,{"key":16,"text":17,"correct":18},"B","暂定金额的数量一般由业主在招标文件中明确",true,{"key":20,"text":21,"correct":18},"C","承包商在施工中无权做主使用暂定金额",{"key":23,"text":24,"correct":14},"D","暂定金额只能用于应对意外情况引起的损失",{"key":26,"text":27,"correct":18},"E","暂定金额应按照业主工程师的指令与决定，全部或部分使用","BCE","暂定金额是业主在招标文件中明确规定了数额的一笔资金，标明用于工程施工，或供应货物与材料，或提供服务，或以应付意外情况，亦称待定金额或备用金。每个承包商在投标报价时均应将此暂定金额数计人工程总报价，但承包商元权做主使用此金额，这些项目的费用将按照业主工程师的指示与决定，全部或部分使用。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]