[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139750":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139750,798,1,"单选题","国际工程项目招标中，如果业主规定了暂定工程量的分项内容和暂定总价款，且规定所有投标人都必须在总报价中加入这笔固定金额，则投标人对该暂定工程的报价策略是（ ). (2013)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单价可适当降低",false,{"key":16,"text":17,"correct":14},"B","总价应适当降低",{"key":19,"text":20,"correct":14},"C","总价可适当提高",{"key":22,"text":23,"correct":24},"D","单价可适当提高",true,"业主规定了暂定工程量的分项内容和暂定总价款，并规定所有投标人都必须在总报价中加入这笔固定金额，但由于分项工程量不很准确，允许将来按投标人所报单价和实际完成的工程量付款；由于暂定总价款是固定的，对各投标人的总报价水平竞争力没有任何影响，因此，投标时应当对暂定工程量的单价适当提高。这样做，既不会因今后工程量变更而吃亏，也不会削弱投标报价的竞争力。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]