[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139737,798,1,"单选题","（2020年真题）根据《建设工程工程量清单计价规范》，关于单价合同计量的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人可以在任何方便的时候计量，计量结果有效",false,{"key":16,"text":17,"correct":14},"B","承包人收到计量的通知后不跟人参加，则发包人的计量结果无效",{"key":19,"text":20,"correct":14},"C","承包人为保证施工质量超出施工图纸范围实施的工程量，应该予以计量",{"key":22,"text":23,"correct":24},"D","发包人应在计量前24小时通知到承包人，无论承包人是否参加，计量结果有效",true,"P260-262 A选项错误，发包人不按照约定时间通知承包人，致使承包人未能派人参加计量，计量结果无效。 B选项错误，承包人收到通知后不派人参加计量，视为认可发包人的计量结果； C选项错误，监理工程师对承包人超出设计图纸要去增加的工程量和自身原因造成返工的工程量，不予计量。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]