[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139736,798,1,"单选题","（2020年真题）根据《建设工程施工合同（示范文本）》关于工程保修期的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人未经竣工验收擅自使用工程的保修期，自转移占有之日起算",true,{"key":16,"text":17,"correct":18},"B","各分部工程的保修期应该是相同的",false,{"key":20,"text":21,"correct":18},"C","工程保修期从工程完工之日起起算",{"key":23,"text":24,"correct":18},"D","工程保修期可以根据具体情况适当低于法定最低保修年限","P298-300 工程保修期从工程竣工验收合格之日起算。具体分部分项工程的保修期由合同当事人约定，但不得低于法定最低保修年限。发包人未经竣工验收擅自使用工程的，保修期自转移占有之日起算。故正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]