[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139734,798,1,"单选题","（2020年真题）根据《建设工程施工合同（示范文本）》，质量保证金扣留的方式原则上采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在支付工程进度款时逐次扣留",true,{"key":16,"text":17,"correct":18},"B","工程竣工结算时一次性扣留",false,{"key":20,"text":21,"correct":18},"C","按照里程碑扣留",{"key":23,"text":24,"correct":18},"D","签订合同后一次性扣留","P298-300 质量保证金的扣留有以下三种方式：（1）在支付工程进度款时逐次扣留（原则上采用这种方式）；（2）工程竣工结算时一次性扣留质量保证金；（3）双方约定的其他扣留方式。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]