[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139731":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139731,798,1,"单选题","（2020年真题）某工程施工时处于当地正常的雨季，导致工期延误.在工期延误期间又出现XX变化。根据《建设工程工程量清单计价规范》，对由此增加的费用和延误的工期正确的处理方式（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用，工期均有发包人承担",false,{"key":16,"text":17,"correct":14},"B","费用由发包人承担，工期由承包人承担",{"key":19,"text":20,"correct":21},"C","费用，工期均由承包人承担",true,{"key":23,"text":24,"correct":14},"D","费用由承包人承担，工期由发包人承担","P263-274 正常的雨季属于一个有经验的承包商可预见的风险，由此增加的费用和延误的工期由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]