[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139730,798,1,"单选题","（2020年真题）根据《建设工程施工合同（示范文本）》，因设计单位提出设计变更，变更后已标价工程量清单中没有相同及类似变更项目单价的，变更估价申请应由（ ）提出。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",true,{"key":16,"text":17,"correct":18},"B","监理人",false,{"key":20,"text":21,"correct":18},"C","发包人",{"key":23,"text":24,"correct":18},"D","设计人","P274-278 承包人应在收到变更指示后14天内，向监理人提交变更估价申请。监理人应在收到承包人提交的变更估价申请后7天内审查完毕并报送发包人，监理人对变更估价申请有异议,通知承包人修改后重新提交。发包人应在承包人提交变更估价申请后14天内审批完毕。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]