[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139728,798,1,"单选题","（2020年真题）某施工项目因80年一遇的特大暴雨停工10天，承包人在停工期间按照发包人要求照管工程发生费用2万元，承包人施工机具损坏损失10万元，已经建成的永久工程损坏损失20万元，之后应发包人要求修复被暴雨冲毁的道路花费2.5万元，修复道路时因施工质量问题发生返工费用1万元。根据《建设工程施工合同（示范文本）》，以上事件产生的费用和损失中，承包人应承担（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","21.0",false,{"key":16,"text":17,"correct":14},"B","13.5",{"key":19,"text":20,"correct":21},"C","11.0",true,{"key":23,"text":24,"correct":14},"D","10.0","P263-274 承包人施工设备的损坏由承包人承担；因施工质量问题发生返工费用由承包人承担。10+1=11万元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]