[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139727":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139727,798,1,"单选题","（2020年真题）根据《建设工程工程量清单计价规范》，工程实施过程中，发包人要求合同工程提前竣工的，应采取的做法是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","下达变更指令，要求承包人必须提前竣工并支付，由此增加的赶工费用",false,{"key":16,"text":17,"correct":14},"B","增加合同补充条款，要求承包人采取加快工程进度措施，不承担赶工费用",{"key":19,"text":20,"correct":21},"C","征得承包人同意后，与承包人商定采取加快工程进度的措施，并承担由此增加的赶工费用",true,{"key":23,"text":24,"correct":14},"D","自行将工期压缩到合同工期的80%，并要求承包人按期完工","P263-274 工程实施过程中，发包人要求合同工程提前竣工的，应征得承包人同意后与承包人商定采取加快工程进度的措施，并应修订合同工程进度计划。发包人应承担承包人由此增加的提前竣工（赶工补偿）费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]