[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139725":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139725,798,2,"多选题","（2019年真题）根据《标准施工招标文件》，承包人可同时索赔工期和费用的情形有（）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人遇到不利物质条件",true,{"key":16,"text":17,"correct":14},"B","施工过程发现文物",{"key":19,"text":20,"correct":21},"C","法律变化引起价格调整",false,{"key":23,"text":24,"correct":21},"D","发包人要求向承包人提前交付工程设备",{"key":26,"text":27,"correct":21},"E","承包人遇到异常恶劣的气候条件","AB","P272-281",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]