[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139722,798,1,"单选题","（2019年真题）某工程在施工过程中因不可抗力造成如下损失:永久工程损坏修复费用16万元，承包人受伤人员医药费4万元，施工机具损害损失6万元，应发包人要求赶工发生费用2万元，停工期间应发包人要求承包人清理现场费用4万元。承包人及时向项目监理机构提出索赔申请，并附有相关证明材料。根据《建设工程施工合同(示范文本)》，项目监理机构应批准的索赔金额为( )万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","22",true,{"key":23,"text":24,"correct":14},"D","32","P257-268 不可抗力导致的人员伤亡、财产损失、费用增加和(或)工期延误等后果，由合同当事人按以下原则承担: 1.永久工程、已运至施工现场的材料和工程设备的损坏，以及因工程损坏造成的第三人人员伤亡和财产损失由发包人承担; 2.承包人施工设备的损坏由承包人承担; 3.发包人和承包人承担各自人员伤亡和财产的损失； 4.因不可抗力引起或将引起工期延误，发包人要求赶工的，由此增加的赶工费用由发包人承担; 承包人在停工期间按照发包人要求照管、清理和修复工程的费用由发包人承担。所以索赔金额为16+2+4=22万元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]