[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139721":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139721,798,1,"单选题","（2019年真题）某混凝土工程招标清单工程量为200m3，合同约定的综合单价为600元\u002Fm3，当实际完成并监理工程师确认的工程量超过清单工程量15%时可调整综合单价，调价系数为0.9。施工过程中，因设计变更导致实际工程量为250m3。则该混凝土工程的工程价款为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12.00",false,{"key":16,"text":17,"correct":18},"B","14.88",true,{"key":20,"text":21,"correct":14},"C","14.74",{"key":23,"text":24,"correct":14},"D","15.00","P257-268 超出工程量百分比：（250-200）\u002F200=25%>15%，需调价。 超过15%的工程量：250-200×（1+15%）=20m3； 超过部分的综合单价：600×0.9=540元\u002Fm3。 故工程款：230×600+20×540=148800元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]