[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139716":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139716,798,1,"单选题","（2019年真题）根据《建设工程工程量清单计价规范》，工程量清单计价的某分部分项工程综合单价为500元\u002Fm3，其中暂估材料单价300元，管理费率5%，利润率7%，工程实施后，暂估材料的单价确定为350元。结算时该分部分项工程综合单价为（）元\u002Fm3。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","350.00",false,{"key":16,"text":17,"correct":14},"B","392.00",{"key":19,"text":20,"correct":21},"C","550.00",true,{"key":23,"text":24,"correct":14},"D","556.18","P257-268 暂估材料或工程设备的单价确定后,在综合单价中只应取代原暂估单价,不应再在综合单价中涉及企业管理费或利润等其他费的变动。则只需要将原暂估材料价格350元取代原暂估材料单价300，该分部分项工程综合单价为550元\u002Fm3。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]