[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139715,798,1,"单选题","某工程随工合同约定根据价格调整公式调整合同价，已知不调值部分占合同价的比例为15%，可参与调值部分的费用类型、占合同总价的比例和相关价格指数见下表，若结算当月完成的合同额为1000万元，则调整后的合同金额为（）。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1050",true,{"key":16,"text":17,"correct":18},"B","1034",false,{"key":20,"text":21,"correct":18},"C","1017",{"key":23,"text":24,"correct":18},"D","1000","1000×15%+1000×0.3×106\u002F101+1000×0.2×105\u002F101+1000×0.25×115\u002F105+1000×0.1×105\u002F102=1049.52≈1050。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]