[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139714":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139714,798,2,"多选题","根据现行《建设工程价款结算暂行办法》，发包人未在合同约定的时间内向承包人支付工程竣工结算价款时，承包人可以采取的措施有（ ). (2013)",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","向发包人催促按约定支付工程结算价款",true,{"key":16,"text":17,"correct":18},"B","将该工程留置不予交付使用",false,{"key":20,"text":21,"correct":14},"C","向发包人要求按银行同期贷款利率支付拖欠工程价款的利息",{"key":23,"text":24,"correct":14},"D","与发包人协商将该工程折价抵款",{"key":26,"text":27,"correct":14},"E","向人民法院申请将该工程依法拍卖","ACDE","承包人可以催告发包人支付结算价款，如达成延期支付协议，承包人应按同期银行贷款利率支付拖欠工程价款的利息。如来达成延期支付协议，承包人可以与发包人协商将该工程折价，或申请人民法院将该工程依法拍卖，承包人就该工程折价或者拍卖的价款。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]