[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139711,798,1,"单选题","工程峻工结算书编制与核对的责任分工是（ ）。 (2012)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人编制，承包人核对",false,{"key":16,"text":17,"correct":14},"B","监理机构编制，发包人核对",{"key":19,"text":20,"correct":21},"C","承包人编制，发包人核对",true,{"key":23,"text":24,"correct":14},"D","造价咨询人编制，承包人核对","竣工结算的程序 1. 承包人递交竣工结算书 2. 发包人进行结算审核 3.工程竣工结算价款的支付",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]