[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139708":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139708,798,2,"多选题","施工合同履行过程中，导致工程量清单缺项并应调整合同价款的原因有() (2015)",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计变更",true,{"key":16,"text":17,"correct":14},"B","施工条件改变",{"key":19,"text":20,"correct":21},"C","承包人投标漏项",false,{"key":23,"text":24,"correct":14},"D","工程量清单编制错误",{"key":26,"text":27,"correct":21},"E","施工技术进步","ABD","导致工程量清单缺项的原因一般属于业主方的原因，包括：设计变更、施工条件改变、工程量清单编制错误。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]