[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139705,798,1,"单选题","采用工程量清单计价的工程在竣工决算时，暂估价中的材料单价应按（ ）。 (2012)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包方自行购买该材料的单价计入综合单价确定",false,{"key":16,"text":17,"correct":18},"B","发、承包双方最终确认价在综合单价中调整",true,{"key":20,"text":21,"correct":14},"C","招标文件中的暂估价定",{"key":23,"text":24,"correct":14},"D","市场价格信息在综合单价中调整","发、承包双方最终确定价在综合单价中调整 发包人在招标工程量清单中给定暂估价的材料、工程设备属于依法必须招标的，由发承包双方以招标的方式选择供应商，确定价格，并应以此为依据取代暂估价，调整合同价款 。 发包人在招标工程量清单中给定暂估价的材料、工程设备不属于依法必须招标的，应由承包人按照合同约定采购，经发包人确认单价后取代暂估价，调整合同价款。 都需要发承包双方确定。题目太老，没有找到原味，可能第三版教材是原文。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]