[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139704":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1139704,798,2,"多选题","关于招标控制价中“暂列金额”的说法，正确的 有（ ） (2012)",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设计图纸详细深入的工程，可适当降低暂列金额",true,{"key":16,"text":17,"correct":14},"B","复杂工程的暂列金额可适当提高",{"key":19,"text":20,"correct":21},"C","暂列金额由材料暂估价和专业工程暂估价两部分组成",false,{"key":23,"text":24,"correct":14},"D","暂列金额的估算要考虑工程环境条件",{"key":26,"text":27,"correct":21},"E","暂列金额应根据拟采用的施工方案估算","ABD","该题目比较综合，由于暂列金额是招标人在工程量清单中列示的一笔款项。用以支付签约时未明确的费用，所以当设计图纸深入详尽，未明确的事项就少，所以暂列金额可以少一些；复杂工程会存在较多未明确事项，所以暂列金额会高一些；选项C是暂估价的内容。 有超纲嫌疑",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]