[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139701":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139701,798,1,"单选题","根据《建设工程价款结算暂行办法》，建设工程承发包双方未在合同中对工程进度款支付时间、支付比例等作约定的，发包人应该在批准工程进度款支付申请的（ ）天内，向承包人支付规定比例范围内的工程进度款。 (2012)",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","28",{"key":19,"text":20,"correct":14},"C","56",{"key":22,"text":23,"correct":24},"D","14",true,"发包人应在收到承包人进度款支付申请后的14天内根据计量结果和合同约定对申请内容予以核实，确认后向承包人出具进度款支付证书。若发承包双方对有的清单项目的计量结果出现争议，发包人应对无争议部分的工程计量结果向承包人出具进度款支付证书。发包人应在签发进度款支付证书后的14天内，按照支付证书列明的金额向承包人支付进度款。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]