[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139690,798,1,"单选题","根据根据《建设工程工程清单计价规范》（GB50500-2013），由于承包人因未在约定的工期内竣工 ，则对原约定竣工日期继续施工的工程，在使用价格调整公式进行价格调整时，应使用的现行价格指数 是（）。（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","原约定竣工日期的价格价格指数",false,{"key":16,"text":17,"correct":18},"B","原约定竣工日期与实际竣工日期的两个价格指数中较低者",true,{"key":20,"text":21,"correct":14},"C","实际竣工日期的价格指数",{"key":23,"text":24,"correct":14},"D","原约定竣工日期与实际竣工日期的两个价格指数中较高者","因承包人原因导致工期延误的，计划进度日期后续工程的价格，应采用计划进度 日期与实际进度日期两者的较低者。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]