[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139686,798,1,"单选题","根据《建设工程工程清单计价规范》（GB50500-2013），采用清单计价的某部分分项工程，招标控 制价的综合单价为350元，承包人投标报价的综合单价为300元，该工程投标报价总价的下浮率为5%，结 算时，该部分分项工程工程量清单工程质量增加了16%，且合同未确定综合单价调整方法，则对该综合 单价的正确处理方式是（）。（2016）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整为257元",false,{"key":16,"text":17,"correct":14},"B","调整为282.63元",{"key":19,"text":20,"correct":21},"C","不做任何调整",true,{"key":23,"text":24,"correct":14},"D","调整为345元","350*（1-5%）*（1-16%）=279.3 300 不作调整。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]