[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139684,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013)，若合同未约定，当工程量清单项目的清单工程量偏差在（）以内时，其综合单价不作调整，执行清单原有的综合单价. (2013)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15%",true,{"key":16,"text":17,"correct":18},"B","5%",false,{"key":20,"text":21,"correct":18},"C","10%",{"key":23,"text":24,"correct":18},"D","20%","若合同无约定的，当工程来给你清单项目的工程量偏差在15%以内的，其综合单价不做调整，执行原有的综合单价。 巳标价工程量清单中有适用于变更工程项目的，应采用该项目的单价；但当工程变更导致该清单项目的工程数量发生变化，且工程量偏差超过1 5 % 。此时，调整的原则为：当工程量增加15%以上时，其增加部分的工程量的综合单价应予调低；当工程量减少 15%以上时，减少后剩余部分的工程量的综合单价应予调高。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]