[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1139683,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），当合同中没有约定时，对于任一招标工程量清单项目，如果因工程变更等原因导致工程量差超过（ ）时，合同单价应进行调整。 (2014)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":18},"B","15%",true,{"key":20,"text":21,"correct":14},"C","10%",{"key":23,"text":24,"correct":14},"D","5%","根据《建设工程工程量清单计价规范》（GB50500 - 2013），对于任一招标工程量清单项目，如果因工程量偏差和工程变更等原因导致工程量偏差超过15 %时，可进行调整。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]