[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139681":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1139681,798,1,"单选题","根据《建设工程工程量清单计价规范》(GB50500—2013)，施工过程中发生的计日工，应按照（ ）计价。 (2015)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已标价工程量清单中的计日工单价",true,{"key":16,"text":17,"correct":18},"B","计日工发生时承包人提出的综合单价",false,{"key":20,"text":21,"correct":18},"C","计日工发生当月市场人工工资单价",{"key":23,"text":24,"correct":18},"D","计日工发生当月造价管理部门发布的人工指导价","计日工是指在施工过程中，承包人完成发包人提出的工程合同范围以外的零星项目或工作，按合同中约定的综合单价计价。 任一计日工项目实施结束后，承包人应按照确认的计日工现场签证报告核实该类项目的工程数量，并应根据核实的工程数量和承包人已标价工程量清单中的计日工单价计算，提出应付价款；已标价工程量清单中没有该类计日工单价的，由发承包双方按工程变更的相关规定商定计日工单价计算",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]