[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1139679,798,1,"单选题","某工程采用工程量清单招标，招标人公布的招标控制价为1亿元。2018真题中标人的投标报价为8900万元。2018真题经调整计算错误后的中标价为9100万元，所有合格投标人的报价平均为9200万元，则该中标人的报价浮动率为（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8.0%",false,{"key":16,"text":17,"correct":14},"B","8.5%",{"key":19,"text":20,"correct":21},"C","9.0%",true,{"key":23,"text":24,"correct":14},"D","110%","本题考查的是工程变更价款的确定。报价浮动率=（1-中标价\u002F招标控制价）×100%=（1-9100\u002F10000）×100%=9%。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]