[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1139678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1139678,798,1,"单选题","某施工项目6月份因异常恶劣的气候条件停工3天，停工费用8万元；之后因停工待图损失3万元，因施工质量不合格，返工费用4万元。根据《标准施工招标文件》，施工承包商可索赔的费用为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":14},"C","7",{"key":22,"text":23,"correct":24},"D","3",true,"本题考查的是施工索赔。对于承包商而言由于施工质量不合格的返工费是其自身原因造成的不可得到索赔；恶劣天气，仅可以得到工期索赔；所以只能得到停工待图的索赔金额即3万元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]